Registration Number (HPBC) 122
Design Checking Duration
Under Constructed Duration
Developer MGW Construction Co.,Ltd.
Storey 23
Building Type Residential
Address No.125/127, Sayar San Road, Yankin Township.
Project Status

Design Status

Project Status
Architecture 1. Document checking is finished.
2.Recommended for Superstructure. (18.11.2016)
Structure 1.Recommended P.L.T (27.9.2013)
2.Remind to submit Foundation and Superstructure Design and Y.C.D.C Letter.(14.9.2015)
3. YCDC Letter for All (8.4.16)
4. Submitted document for All (1.6.16)
5. Recommended for Superstructure. (18.11.2016)
Electrical 1. Sent the remind letter to submit document on (20.3 .2017).
2. Received letter that cause of delay from company. (28.3.15)
3. Sent the 9th remind letter to submit MEP drawing. (8.10.18)
4. Received letter that cause of delay from company. (6.11.18)
5.Sent the11th remind letter to submit MEP drawing. (24.12.18)
6. Design MEP drawing & calculation 3 sets was submitted on (21.1.2019).
7. Not yet presented by developer.
ACMV 1. Sent the remind letter to submit document on (20.3 .2017).
2. Received letter that cause of delay from company. (28.3.15)
3. Sent the 9th remind letter to submit MEP drawing. (8.10.18)
4. Received letter that cause of delay from company. (6.11.18)
5. Sent the11th remind letter to submit MEP drawing. (24.12.18)
6. Design MEP drawing & calculation 3 sets was submitted on (21.1.2019).
7. Not yet presented by developer.
Water and Sanitation 1. Sent the 3rd remind letter to submit MEP drawing. (20.3.2017).
2. Received letter that cause of delay from company. (28.3.17)
3. Sent the 7th remind letter to submit MEP drawing. (23.7.18)
4. Received letter that cause of delay from company. (5.7.18)
5. Sent the 9th remind letter to submit MEP drawing. (8.10.18)
6. Received letter that cause of delay from company. (6.11.18)
7. Sent the11th remind letter to submit MEP drawing. (24.12.18)
8. Design MEP drawing & calculation 3 sets was submitted on (21.1.2019).
9. Not yet presented by developer.