REPUBLIC OF THE UNION OF MYANMAR
Registration Number (HPBC) 186
Design Checking Duration
Under Constructed Duration
Developer Yoma Development Group Co., Ltd.
Storey 2 Tower of 17 Storeyed
Building Type Residential
Address Pan Hlaing Golf Estate, Hlaingtharyar Township.
Project Status

Design Status

Project Status
Architecture 1. Delay From Company.
2. Submit company letter for reason of delaying the project. (28.4.16)
Structure 1. UPLT recommended. (20.7.15)
2. Discussion for UPLT report (3.8.15)
3. Revised UPLT recommended. (31.8.15)
4. Sent confirm letter for pile capacity according to UPLT result. (24.9.15)
5. Remind letter to submit WPLT and design documents. (24.4.16)
6. Submit company letter for reason of delaying the project. (28.4.16)
Electrical 1. Design Drawing was submitted on (12.2.2016).
2. Not presented yet.
3. Submit company letter for reason of delaying the project. (28.4.16)
ACMV 1. Design Drawing was submitted on (12.2.2016).
2. Not presented yet.
3. Submit company letter for reason of delaying the project. (28.4.16)
Water and Sanitation 1.Submit Cal: + drawing (4)sets to CQHP on (11.2.16)
2. Not presented yet.
3. Submit company letter for reason of delaying the project. (28.4.16)