Registration Number (HPBC) | 186 |
Design Checking Duration | |
Under Constructed Duration | |
Developer | Yoma Development Group Co., Ltd. |
Storey | 2 Tower of 17 Storeyed |
Building Type | Residential |
Address | Pan Hlaing Golf Estate, Hlaingtharyar Township. |
Project Status |
Project Status | |
Architecture | 1. Delay From Company. 2. Submit company letter for reason of delaying the project. (28.4.16) |
Structure | 1. UPLT recommended. (20.7.15) 2. Discussion for UPLT report (3.8.15) 3. Revised UPLT recommended. (31.8.15) 4. Sent confirm letter for pile capacity according to UPLT result. (24.9.15) 5. Remind letter to submit WPLT and design documents. (24.4.16) 6. Submit company letter for reason of delaying the project. (28.4.16) |
Electrical | 1. Design Drawing was submitted on (12.2.2016). 2. Not presented yet. 3. Submit company letter for reason of delaying the project. (28.4.16) |
ACMV | 1. Design Drawing was submitted on (12.2.2016). 2. Not presented yet. 3. Submit company letter for reason of delaying the project. (28.4.16) |
Water and Sanitation | 1.Submit Cal: + drawing (4)sets to CQHP on (11.2.16) 2. Not presented yet. 3. Submit company letter for reason of delaying the project. (28.4.16) |