Registration Number (HPBC) 215
Design Checking Duration
Under Constructed Duration
Developer HAGL Myanmar Co.,Ltd.
Storey 2B + (3Nos. of 33 Storey + 2Nos. of 23 Storey Office + 2Nos. of 29 Storey)
Building Type -
Address No.192, Corner of Kabaraye Pagoda Road & Industrial Road.
Project Status

Design Status

Project Status
Architecture 1. Presented Architectural presentation.(29.5.2017)
2. Submit Final Architectural drawing (4) sets for Residential Buildings. (31.10.18)
3. Discussion with foreign Architect and National Counterpart about Residential Buildings. (1.11.2018)
4. Principle Recommended on Architecture, Deep Excavation, Foundation & Structure for Residential Buildings. (19.11.2018)
Structure 1. Recommended for PLT (2.6.2017)
2. Discussion for PLT report. (29.1.2018)
3. Recommended piling. (29.11.2017)
4. Waiting presentation for all design.
5. Comment for overall (6.11.2018)
6. Comment reply for overall from company.(15.11.2018)
7. Principle Recommended on Architecture, Deep Excavation, Foundation & Structure for Residential Buildings. (19.11.2018)
Electrical 1. Presentation(25.3.2019).
2. Comment sent on (1.4.2019).
3. Company submit reasons for the delay (3.5.2019).
4. Company submit reasons for the delay (10.6.2019).
5. Waiting for comment reply.
ACMV 1. Presentation(25.3.2019).
2. Comment sent on (1.4.2019).
3. Company submit reasons for the delay (3.5.2019).
4. Company submit reasons for the delay (10.6.2019).
5. Waiting for comment reply.
Water and Sanitation 1. Presentation(25.3.2019).
2. Comment sent on (1.4.2019).
3. Company submit reasons for the delay(3.5.2019).
4. Company submit reasons for the delay(10.6.2019).
5. Waiting for comment reply.