Registration Number (HPBC) | 231 |
Design Checking Duration | |
Under Constructed Duration | |
Developer | Naing Group Capital Co,ltd |
Storey | Basement + 21/20 Storeyed |
Building Type | - |
Address | No.(467/469), Pyay Road, Kamaryut Township. |
Project Status | Projects List |
Architecture | "1. Received YCDC Approval Architectural drawing (1) set with remark. (20.11.2020) 2. Received request letter for Architectural conceptual presentation.(11.1.2021) 3. Presented Architectural conceptual presentation.(19.1.2021) 4. Sent comment to Company. (25.1.2021) 5. Sent letter to company. (7.7.2021) 6. Phone to Company (Naign Group): to submit Delay letter (28.6.2024) 7.Remind company to submit delay letter.(11.7.2024)" |
---|---|
Structure | |
Electrical | 1. Not yet submitted by developer |
ACMV | 1. Not yet submitted by developer. |
Water and Sanitation | 1. Not yet submitted by developer |